Capabilities Statements:

Northrop Grumman Shipbuilding (NGSB) Facility Abatement

Location: Pascagoula, MS East Bank Facility
ESA South was a subcontractor to Recycled Materials Co.
Period of Performance: 04/08/2010 - 11/5/2010
Contract Amount: $511,729

ESA South, Inc.

850-937-8520

1681 Success Drive

Cantonment, FL 32533

Asbestos Abatement and hazardous materials remediation of numerous buildings throughout the East Bank of the Pascagoula Shipbuilding facility. ESA South, Inc. was charged with the preparation of buildings for complete teardown, demolition and disposal. Sweep (to identify, to isolate, to remove and to dispose) of all asbestos, chemicals, oils, solvents, materials classified as hazardous throughout each building scheduled for demolition on the East Bank of the Pascagoula Shipbuilding facility.

The management team at ESA South has been providing safe and efficient asbestos abatement for nearly 25 years. Prior to beginning any project, a detailed written plan is developed that addresses each step to be taken for every phase of the project. Our client’s particular concerns and daily work schedules are taken into account in order to minimize disruption in the client’s office and projects to be completed quickly, efficiently, and with a limited amount of down time and inconvenience to the customer’s operations. 

Lead based paint is an increasing environmental concern. Studies have shown that inhaling or ingesting lead dust from deteriorating lead base paint can cause elevated blood lead levels, which can eventually cause lead poisoning. ESA’s experience in the field of lead based paint abatement affords us the ability to abate lead via blasting, chemically stripping and mechanical/hand tool cleaning.

1681 Success Drive

Cantonment, FL 32533 

850-937-8520

ESA South was contracted with the removal of asbestos containing material located in building 2 and building 35 in accordance with all requirements of the VA and the EPA. Included in the Scope of work for building 2 was the demolition of 913 SF of wall and chase to remove approximately 194 Ft of pipe insulation, the removal of 406 SF or 9x9 floor tile and mastic, removal of 1,587 SF of 12x12 floor tile and black mastic, and the removal of 220 SF of carpet. The Scope of Work in building 35 included the removal of 2,800 CF of soil inside a crawl space and the removal of pipe insulation to comply with standards.

ESA South was contracted to design and complete the abatement and disposal of lead paint on the walls, ceiling, beams and conduit of the CEP at the Orlando Lake Baldwin Campus. In addition to abatement, this project also included new paint on the walls, roof deck, beams and conduit. Consequently, this project corrected an FCA deficiency by painting exposed roof decking and completing any additional tasks that were identified by Orlando Lake Baldwin Campus Engineering Department.

Design/Build Remove Lead Based Paint at the CEP
Orlando VAMC, FL
Contract Number: VA248-14-J-0223 – Task Order Contract under VISN 8
Period of Performance: 2/24/14 – 11/2014
Contract Amount: $692,179

Design/Build Asbestos Abatement Bldg. 2 and 35
Contract Number: VA248-13-J-5837 – Task Order under VISN 8
Location: Bay Pines VA Medical Center – Bay Pines, FL
Period of Performance: 09/16/2013 - 9/28/2013
Contract Amount: $67,648